Government launches new £5bn ‘Project Gigabit’ with plans to connect up to 140,000 premises in Norfolk in the early phase of the programme, along with vouchers, and connecting public sector buildings.
More than one million hard to reach homes and businesses will have next generation gigabit broadband built to them in the first phase of a £5 billion government infrastructure project.
- First areas to benefit from £5bn government funding for fastest broadband connections to help recovery from the pandemic, growth and levelling up
- Extra £210m worth of vouchers released to help those with slow speeds
- £110m to connect up to 7,000 rural GP surgeries, libraries and schools
- Call for evidence on using satellite and 5G technology to connect very hard to reach areas
More than one million hard to reach homes and businesses will have next generation gigabit broadband built to them in the first phase of a £5 billion government infrastructure project.
Up to 510,000 homes and businesses in Cambridgeshire, Cornwall, Cumbria, Dorset, Durham, Essex, Northumberland, South Tyneside and Tees Valley will be the first to benefit as part of ‘Project Gigabit’.
Their available speeds will rocket to more than 1,000 megabits or one gigabit per second. It means families no longer having to battle over bandwidth and will give people in rural areas the freedom to live and work more flexibly. Contracts for these first areas will go to tender in the spring with spades in the ground in the first half of 2022.
In June the government expects to announce the next procurements to connect up to 640,000 premises in Norfolk, Shropshire, Suffolk, Worcestershire, Hampshire and the Isle of Wight.
Commenting James said: "Improving broadband speeds is an issue I have campaigned on so I am pleased to that Norfolk will benefit from the early phase of the rollout. Now I will be working to ensure North West Norfolk benefits from this welcome investment."
The government-funded projects will prioritise areas that currently have slow connections and which would otherwise have been left behind in broadband companies’ rollout plans.
Gigabit broadband is being rolled out rapidly - from one in ten households in 2019 to almost two in five today. The UK is on track for one of the fastest rollouts in Europe and for half of all households to have access to gigabit speeds by the end of this year.
Project Gigabit will accelerate our recovery from covid, fire up high growth sectors like tech and the creative industries and level up the country, spreading wealth and creating jobs the breadth of Britain.
The successful Gigabit Broadband Voucher Scheme is also being relaunched with up to £210 million to give people in eligible rural areas immediate financial help to get gigabit speeds.
On top of this the government is making up to £110 million available to connect public sector buildings - such as GP surgeries, libraries and schools - in the hardest to reach parts of the UK with this revolutionary infrastructure.
Prime Minister Boris Johnson said:
Project Gigabit is the rocket boost that we need to get lightning-fast broadband to all areas of the country. This broadband revolution will fire up people’s businesses and homes, and the vital public services that we all rely on, so we can continue to level up and build back better from this pandemic.
Delivery Plan for Project Gigabit
The government is today responding to its public consultation Planning for Gigabit Delivery in 2021 which sought views on how to spend its record £5 billion funding commitment for gigabit broadband in hard to reach areas.
It outlined a strategy to make local, regional and cross-regional contracts available for broadband network providers of all different sizes to bid for. The first procurements to be announced are:
- 110,000 to 130,000 premises in Durham, South Tyneside & Tees Valley and areas of Northumberland - including Darlington, Stockton, Hartlepool, Middlesbrough, Redcar and Cleveland, Sunderland, Gateshead and South Tyneside
- 60,000 to 80,000 premises in West Cumbria including in the Lake District National Park
- 30,000 to 50,000 premises in North and West Northumberland and East Cumbria - including Brampton and Rothbury
- 120,00 to 140,000 premises in Cambridgeshire and adjacent areas - including Peterborough and parts of Northamptonshire, Essex, Hertfordshire and Rutland
- 40,000 to 60,000 premises in East Cornwall - including Launceston, Callington and Looe
- 30,000 to 50,000 premises in West Cornwall - including in Cambourne-Pool-Redruth and Penzance and the Isles of Scilly
On top of these six regional contracts, there will be further local supplier contracts in Essex and Dorset. This first release of procurement contracts for England follows central Scotland recently being named as the first area to receive Project Gigabit funding. The UK and Scottish government are discussing the potential for further Project Gigabit contracts in Scotland, which could be delivered alongside Scotland’s R100 programme.
There are already major programmes delivering gigabit broadband in the devolved administrations, including R100 in Scotland and Phase 3 of the UK government’s previous superfast broadband programme in Wales. Project Gigabit builds on the £2.6 billion Superfast programme, which is now predominantly funding gigabit-capable rather than superfast connections.
In Northern Ireland, the UK government has invested £150 million in Project Stratum, which will connect approximately 76,000 homes and businesses to gigabit broadband. The first live connections under the scheme were delivered last week in County Tyrone.
Additionally between September and December 2020, the government approved a further £490 million in new contracts via the Superfast Broadband programme across the UK to connect a further 172,000 premises to gigabit in Scotland, Cheshire, West Yorkshire, North Yorkshire, Lincolnshire, North Lincolnshire, Devon and Somerset.
Gigabit Broadband Voucher Scheme
For rural homes and businesses across the UK currently struggling with slow broadband speeds, the government is investing up to £210 million to build on the success of its Gigabit Broadband Voucher Scheme.
Launched in March 2018, the scheme provided eligible areas across the UK with vouchers to cover the installation costs of bringing gigabit connectivity to people’s homes and businesses. So far more than 66,000 vouchers worth up to £127 million have been issued to premises across the UK.
The new vouchers worth up to £1,500 for residents and up to £3,500 for businesses will go live on 8 April 2021 and mean that rural areas will not have to wait for supplier contracts under Project Gigabit to reach them.
There will be a new online postcode checker available so people can check if their home or business is eligible for a voucher.
Public sector buildings
Project Gigabit will invest up to £110 million to connect public buildings such as rural schools, doctors’ surgeries and libraries to gigabit broadband. This will help GPs provide remote video consultations and allow whole classes of schoolchildren to be online at once with no interruptions.
The government wants to connect up to 7,000 rural public buildings in order to improve public services. They will act as hubs to get gigabit-capable networks into the heart of countryside communities and incentivise other broadband companies to build off them.
The Department for Digital, Culture Media and Sport (DCMS) continues to engage with local bodies and government departments to identify suitable projects, and expects the first of these to be progressed this summer.
Very Hard to Reach Areas - Call for evidence
The UK has some very remote places that may be too expensive to build a gigabit-capable broadband network to, even with substantial public subsidy.
Thanks to completed or pending government-funded projects, less than 0.3% of the country or less than 100,000 premises are likely to fall into this category.
For these premises, which are mainly located in remote and isolated locations in Scotland and Wales, and some National Parks in England, a call for evidence has been launched to explore the barriers to improving their broadband and how innovative new technologies might help change this.
This could lead to the government encouraging industry to use new wireless equipment, low-orbit satellites or high altitude platforms to beam faster connections to far-flung homes and businesses.
The government has already made investments in wireless, satellite and hybrid-fibre technologies, and continues to explore emerging technologies in this area. Some of these technologies are also gigabit-capable and eligible for UK Gigabit Programme funding today.
ENDS
Notes to Editors
Alongside the Delivery Plan for Project Gigabit, DCMS has today published an update on the work of its Barrier Busting Taskforce. The Taskforce has played a key role in improving the environment for digital infrastructure investment and deployment. It has already delivered a number of key changes, including:
- Launching the Digital Connectivity Portal, to provide guidance to both operators, local authorities, landowners as well as other stakeholders, on core issues including best practice guides to street works, the Electronic Communications Code and how to engage with operators.
- Working closely with the Department for Transport (DfT) to make it easier for operators to access roads for digital infrastructure deployment. This has included delivering the new Street Manager service, which Street Works UK described as bringing “the coordination of street works into the digital age”.
- Passing the Telecommunications Infrastructure (Leasehold Property) Act to address the issue of unresponsive landlords holding up digital infrastructure deployment and support the 10 million people living in blocks of flats in the UK.
- Exploring further barriers in relation to access to land through a consultation on potential reforms to the Electronic Communications Code.
- Coordinating a series of workshops for Code users, focused on delivering better ways of working in key areas such as identifying commonly agreed positions for fixed and mobile template agreements, ensuring compliance with the Ofcom Code of Practice and an agreed approach to communications.
- Working with property developers and across Whitehall to create a comprehensive solution which will ensure new build developments are built with fast, reliable, resilient, gigabit-capable connections.
- Publishing consultations on reforms to planning regulations for mobile network development, to support the deployment of 5G infrastructure and extend existing mobile coverage.
- With Ofcom, publishing a 5G technology guide to support councils and counter misinformation about 5G.
- Engaging with local authorities to promote best practice and help facilitate deployment, including the appointment of designated Digital Champions, publication of guidance on land access and valuation, and resolution of operator performance issues.
- Resolving dozens of small-scale real-world barriers to deployment.
The Budget introduced a world-leading super deduction tax break. Over the next two financial years ending in March 2023, companies will be able to cut their tax bill by up to 25p for every £1 they invest in qualifying new plant and machinery assets, ensuring the UK capital allowances regime is amongst the world’s most competitive. This will give companies a strong incentive to make additional investments, including telecoms firms investing in gigabit network build